Marino boosting South West roads

Member for Forrest Nola Marino said 14 road upgrades have now commenced in Forrest as part of the Turnbull Government’s $1.86 billion into the Roads to Recovery Programme this financial year.

“14 road upgrades is a great result for the South West local communities,” Mrs Marino said.

Below is a list of the projects now underway.

Mrs Marino was optimistic about more road upgrades being announced in the South West.

“There are many roads in the South West which need work and I’ll be fighting to ensure more roads are upgraded,” Mrs Marino said.

Acacia Street, Bunbury – Upper Esplanade to Scott Street.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $210,000

Macnish Close, Bunbury – Acacia Street to Cul De Sac.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $10,000

Medici Lane – Victoria Street to End of Laneway.

Pavement repair where required, primer seal and asphalt reseal.
Finish – Dec 2017 $20,000

Pickersgill Street, Bunbury – Acacia Street to Roberts Crescent.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $119,000

Sherry Street, Bunbury – Acacia Street to the cul-de-sac.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $94,000

Simpson Avenue, Bunbury – Scott Street to the dead end just past Pickersgill Street.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $59,000

Swansen Avenue, Bunbury – Acacia Street to Cul De Sac.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $18,000

Upper Esplanade, Bunbury – Scott Street to Acacia Street.

Replace kerbing. Upgrade drainage pit lids to new. Profile, primer seal and reseal road surface with asphalt.
Finish – May 2018 $130,000

Florence Road (Rural Road) – The full length of this road between Kaloorup Road and Westbrook Glen

100mm of gravel will be applied to the road surface and shaped for safe vehicle travel.
Finish – Sep 2017 $35,000

Taylor Road – From Hairpin Road for 1140 metres to dead end

100mm of gravel will be applied to the road surface and shaped for safe vehicle travel.
Finish – Sep 2017 $48,000

Boodjidup Road, Margaret River

Full width asphalt overlay of the road.
Finish – Sep 2017 $100,000

Mansfield Avenue, Margaret River

Full width asphalt overlay of the road.
Finish – Sep 2017 $44,000

Redgate Road, Witchcliffe

Full width reseal of road surface, and full width asphalt overlay of the road surface at the start of the road.
Finish – Sep 2017 $160,000

Riverdale Road – Between Meredith Road and Forrest Highway

Reconstruct old gravel and limestone pavement and seal to seven metres wide.
Finish – Nov 2017 $259,686